Project team mobilised including SNCF experts in rolling stock, driver training and timetabling; and Govia experts in rolling stock and depots from the Southern Region New Trains Programme. Partnership with the Olympic Transport Authority begins. |
Southeastern starts training drivers with expert support from SNCF. First four high-speed units arrive. Testing begins. |
Detailed planning and preparations continue. |
March - November: Delivery of remaining 24 high-speed units New control centre opens in Ashford December: Channel Tunnel Rail Link begins service - the high-speed rail revolution comes to Kent and East Sussex |
|||